The roof has been completed and the septic tank has been lined and covered with slab. Construction of the water tower and drainage is ongoing and electrical work is set to start soon. The fabrication of steel doors, steel windows, metal railings and shelves for the installation of the solar batteries is already in progress. The road is a nightmare for now as two attempts made trying to convey materials failed. A week ago, we loaded a truck with cement to be transported to the site but it got stuck on the way and took three days before it could be removed. We had to use motor bikes to transport the cement from the point where it got stuck to the building site in fear of it getting damaged.
Alimamy Samura
SHF Country Director